Difficult location for a new sewage installation

The Gravity Drilling Technology also includes installations made of PE pipes. One of such projects was the construction of a sanitary sewage connection for a single-family residential building in the Redłowo estate in Gdynia. The installation of the PE-RC DN160 pipe should be 37 meters long, with a 5.5% gravity drop, between the existing DN1200 well and the excavation.

plan
Installation project
profil
Installation project

In the case of this project, it was difficult to locate the installation among dense residential buildings and home gardens. In the area of work, there was a significant slope of the terrain and slopes limiting the maneuvering of any construction equipment.

lokalizacja
Installation location

Initially, it was assumed that the installation would be performed with the use of a HDD drilling rig, but due to the above-mentioned field inconveniences, the company declaring execution with the use of HDD eventually withdrew from the implementation after an on-site visit. The installation was considered with the use of a pneumatic jacking machine, commonly known as a mole. However, there was a high risk that the jacking technology, uncontrollable and without the possibility of locating and possible corrections of the set trajectory, on a length of 37 meters, would fail, the mole would not hit the well, we would not get the desired drop. In addition, vibrations and shocks caused by the mole's work may cause damage to neighboring buildings and other facilities such as retaining walls and brick fences. We know of projects in which the use of a mole for a typical culvert under the road caused damage, cracks in the facades of buildings adjacent to the works. The strength of such an impact can be approximated on the basis of the ability to transmit vibrations through a given soil medium, but it is associated with additional expertise and soil tests. The use of a mole in such a close development is a high risk related to possible claims for possible damage. Moreover, such work would be very troublesome. It was impossible to install the installation using an open trench, due to the co-location of the installation with a 1.5 meter wide technical belt belonging to the city. In the end, it turned out that the technology with the use of the Gravity Drilling Rig is the only effective and most economical solution for this project.

studnia startowa
Location of the S3 starting well
studnia startowa 00
The depth of the starting well S3
wiertnica do studni
Installation of a drilling rig in a well
przygotowanie zerdzi
Preparation of installation rods
montaz wiertnicy w studni
Installation of the drilling rig in the S3 well
wiertnica do studni 04
Installation of the drilling rig in the S3 well
montaz lokalizatora
Mounting the locator transmitter in the drill head
pomiary
Measurements during assembly of the drilling rig at the correct depth in the S3 well
studnia startowa 03
Connecting the hydraulic hoses responsible for the drive and control of the Gravity Drilling Rig
przewiertak
Fitting the drilling rig with a head enabling drilling through the wall of the S3 starting well
wykop 01
Preparation of the final chamber
wiercenie 02
Pilot drilling from the S3 starting well to the ending chamber
wiercenie 01
Pilot drilling from the S3 starting well to the ending chamber
wiercenie w studni 02
Pilot drilling from the S3 starting well to the ending chamber
lokalizacja
Verification of the bore path
przewiert do wykopu 01
Reaching the final trench with a pilot drilling
przewiercenie 03
Equipping the rod with a head for drilling soil with simultaneous pulling of the pipe
mocowanie pe 01
Connecting the pipe to a reaming head equipped with a swivel
zabezpieczenie koncowki rury
Protection of the pipe end against the ingress of soil and contamination
wciaganie pe 01
Pulling the pipe from the end chamber into the S3 start well
wciaganie pe 02
Pulling the pipe from the end chamber into the S3 start well
wciaganie studnia 01
Pulling the pipe into the S3 starting well
koronowanie 00
Reaming the hole in the S3 starting well and pulling the end of the pipe
koniec 02
Reaching the starting well through the reaming head with the installed pipe
koniec 03
Pulling the end of the pipe to be installed into the S3 starting well
wciagnieta rura
Pipe installed in the S3 well

The advantage of the Gravity Drilling technology, apart from the efficiency in drilling and accuracy in the implementation of precise installations, is also the mobility of the devices included in the drilling set. All devices are placed in a compact car body. This allows you to carry out work virtually anywhere, even densely built-up and with difficult access.

man 01
A technical vehicle with full drilling equipment
agregat hydr
Component of the drilling unit - hydraulic unit for driving and controlling the drilling rig

 

 

You can read about other selected projects by clicking on the picture below:

banner realizacje ang1